World Bank/Lagos State Government

About Project:

Borrower Completion Report and Beneficiary Impact Study-Lagos Metropolitan
Development and Governance Project Lagos Metropolitan Development and Governance Project (LMDGP) is a World Bank assisted project of the Lagos State Government. The primary project objective of the LMDGP was to increase sustainable access to basic urban services through investment in critical infrastructure. The project provided infrastructural development in nine of the
biggest slums in Lagos and also addressed issues of flooding faced by the State, water and sanitation, education, primary health care, roads and drainage, markets, community recreation, and citizen’s mediation centres. In addition, the project was intended to improve Governance in the State.
In accordance with World Bank practice, VIPCG was contracted by the Lagos state Government Project Office to undertake a project completion review and develop a report for submission to the World Bank. The report detailed the achievement of project outcomes, project impact, project execution activities, lessons learned, financial management reports, and the issues and challenges of project implementation and how they were addressed. In addition, we were contracted to carry out a beneficiary impact study and develop a report for submission to the World Bank.

STATEMENT OF WORK DELIVERED:

  •  Review of project documents including Project design and development
    documents, Accounting, Monitoring and Evaluation records, all project reports.
  • Interview of all key project office personnel
  • Synthesis and draft report development
  • Draft report review with the State Project Implementation Unit (Borrower Completion Report and Beneficiary Impact Study Report)
  • Submission of final Borrower’s Completion Report and Beneficiary Impact Study report

Posted on:

August 1, 2013

Client:

World Bank/Lagos State Government. August - October 2013

PROJECT STAFF

S/N STAFF MEMBER ROLE ON THE PROJECT

1 Vicky Idoko-Pope
Lead Consultant

2 Olushola John E.
2 nd Lead Consultant, Institutional Reform Specialist, Project Manager

3 Patrick Ini
1 st Lead, Beneficiary Impact Survey, report Writing

4 Emmanuel Osagie
2 nd Lead, Beneficiary Impact Survey, report Writing

5 Various Surveyors in each State

PROJECT REFERENCE

DR. Adedayo Oguntunde Project Director, LMDGP